Home / Practice areas / Planning Law

Retention Permission

Retention permission is planning permission for development that has already been carried out. It is the ordinary way of regularising an extension, a conversion or a change of use that was made without permission or that departed from the permission granted.

When it is needed

Works that needed permission and did not get it are unauthorised, and so are works that were not built in accordance with the permission or its conditions. The commonest examples are extensions larger than the exemptions allow, attic and garage conversions, garden rooms used as living accommodation, houses built in a different position or to a different design from the approved drawings, and changes in the use of commercial premises. The problem usually surfaces when the property is being sold or remortgaged, because the buyer's solicitor and the lender will ask for evidence of compliance.

How the application is made

An application to retain development is made to the planning authority in the same way as any other application, with public notices, drawings and the right of third parties to make submissions. The authority considers the development on its planning merits. That the work is already done is not a reason to grant permission, and it is not in itself a reason to refuse. Permission is often granted subject to conditions requiring alterations, and a refusal may be appealed to An Coimisiún Pleanála. An architect, engineer or planning consultant ordinarily prepares the application, and we advise on the legal position and on how the application fits with any sale or enforcement process.

When retention is not available

Retention cannot be used for development that required an environmental impact assessment, a screening for one, or an appropriate assessment under the Habitats Directive. Under the Planning and Development Act 2000 such development could be regularised only by substitute consent. Under the Planning and Development Act 2024 the equivalent is retrospective consent, which is sought directly from An Coimisiún Pleanála and granted only in exceptional circumstances. For development in rural areas or near protected sites, whether screening was required is therefore the first question to ask, before any application is drafted.

The seven year rule

A planning authority generally cannot take enforcement action more than seven years after unauthorised development began. That protects the owner from enforcement. It does not make the development authorised. A buyer may still object to it, a lender may decline it as security, and because works to an unauthorised structure are not exempted development, later alterations that would otherwise be exempt may need permission. Retention permission cures those problems. The passing of time does not.

Retention and enforcement

An application for retention does not of itself stop enforcement action that is under way, although a court asked to grant an injunction may take a genuine pending application into account. A person who has received a warning letter should take advice on both together. See planning enforcement.

Before a sale

The best time to deal with unauthorised works is before the property goes to market. We arrange for the planning history to be compared with what is on the ground, advise whether a declaration that the works were exempt would resolve the matter more simply than an application, and where retention is needed, plan the sale around the time an application and any appeal will take. See planning permission when buying a home.

Common questions

How long does retention permission take?

A planning authority ordinarily decides an application within eight weeks, but requests for further information and any appeal to An Coimisiún Pleanála can add several months. A seller should allow for this before putting a property on the market.

Can retention permission be refused?

Yes. The application is decided on its planning merits, and if it is refused the development remains unauthorised and the authority may take enforcement action. A refusal can be appealed to An Coimisiún Pleanála within four weeks.

Do I need retention permission if the works are more than seven years old?

Enforcement action is generally barred after seven years, but the development is still unauthorised. If a buyer or lender requires the position to be regularised, or you wish to carry out further works, retention permission will still be needed.

Reviewed by Robert Bourke, Principal Solicitor, on 26 November 2026.

Download our briefing on retention permission, appeals and judicial review as a PDF